Ventura Blvd. and Brightleaf Update

Dear Resident,

Construction continues in your neighborhood as part of the above mentioned project. On-going activities consist of the following:

  • Spray Prime Oil (prior to asphalt placement)
  • Install hot mix asphalt concrete (HMAC)

Friday, 3/15/2019 - Prime oil will be sprayed on Ventura and Brightleaf in preparation of asphalt being placed - from Brightleaf to Chippewa Blvd Starting Saturday, 3/15/2019

PLEASE NOTE: Please do not drive on the newly placed prime and find another place to park if you can. If you have to, be careful and drive through this area slowly after prime has been sprayed so it will not splash up on the underneath side of all vehicles.

Flaggers and traffic control devices are in place and we continue to strive to maintain continued access throughout - please be cautious and alert throughout the construction areas. You may experience periods where it seems the road is unpassable but flaggers will guide you as needed for continued access.

Communication with residents will be accomplished via e-mail and the distribution of flyers. If you would like to be notified via email - please send an email to [email protected] that includes your name and address of your residence.