General Sherman Construction Update 1/15/20

Permanent power has been turned on to the building. Sprinkler drops, science room eye wash valves, electric control to HVAC valves, and speakers have been installed on the second floor of the two story classroom section of the building while electric devices and lights are being installed. On the first floor, speakers, sprinkler drops, and ceiling grids are being installed. In the main entrance section, the metal roof in the entry is complete as well as the first coat of paint in the media center. In the cafeteria section, stage area drywall is being installed and the ceiling is being painted. Data wire is being installed.

Steve Wigton
Superintendent