01/24/2022 | Press release | Distributed by Public on 01/24/2022 02:40
The Petroleum Safety Authority Norway (PSA) has carried out an audit of Vår Energi and their management of the upgrading of structures and maritime systems on the Jotun FPSO.
The audit was carried out in the period 23 November to 8 December 2021.
The objective of the audit was to verify that the integrity of structures and maritime systems during the extended operational period is being safeguarded in accordance with the requirements of the HSE regulations.
We identified two non-conformities, concerning:
We also observed four factors that we have chosen to categorize as improvement points. These concerned:
We have asked Vår Energi to report by 28 January 2022 on how the non-conformities will be addressed and for their assessment of the improvement points observed.