Timeline Update- Fire Hydrant Installation

Timeline Update- Fire Hydrant Installation

PROJECT NAME: Install Fire Hydrant

PROJECT LOCATION: Near 22 Hudson Place

PROJECT DESCRIPTION & GOAL: Install new hydrant for improved fire flow

PROJECT START DATE & TIME: Wednesday January 26, 2022 @ 8:00am

SCHEDULED PHASE COMPLETION DATES: Thursday, January 27, 2022 @ 3:00pm

LOCAL IMPACTS: Traffic will be reduced to 1 lane around the project zone with the possibility of a detour periodically throughout the project. Odd number residences from 3- 15 Hudson Pl will experience temporary water interruptions, particularly from 8am -12pm on Wednesday, January 26, 2022 . Local traffic delays should be expected.

For additional information contact: Nick Thomas, Matt Sledjeski or Scott Gibson, DPW, Water & Sewer Division at (607) 272-1717