On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
-
Modular block retaining wall installation
-
Multi-use trail installation
-
Irrigation water line installation
-
Pond liner installation
-
Landscaping improvements
-
Sewer pipe testing
-
Remaining sheet pile wall installation near Exchange Way
Flood Mitigation Phase 2
-
Breckenridge Industrial Court bridge construction
-
Sanitary sewer junction chamber excavation, shoring and construction
-
Sanitary sewer piping and structure(s) installation
-
Sheet pile wall installation along Black Creek near Breckenridge Material Co.
Deer Creek Greenway Connector Part A
-
Roadway installation
-
Subgrade remediation beneath the multi-use trail
-
Multi-use trail installation
-
Construction of dumpster enclosures near Brazeau and Mary avenues
-
Permeable paver parking lot construction
Event Lawn/Comfort Station
-
Exterior stone are complete
-
Painting of restroom ceilings and event space
-
Insulation and wood siding installation
-
Completion of MEP trim in all areas
-
Construction of footings for Food Truck Plaza light poles
MoDOT Manchester Road Improvements
-
Demo, grading and utility work
-
Flatwork installation(s)
-
Pedestrian underpass construction
-
Manchester Road closures and intersection work at Hanley Road
-
Black Creek Bridge construction
Site Cameras
See a live view of work on Brentwood Bound through the "Site Cameras" link at the top of the home page of www.BrentwoodBound.org.
Learn more about Brentwood Bound at www.BrentwoodBound.org.