City Projects
North End pavement replacement project
A contractor working for the City will remove and replace street pavement, water lines, and ADA-standard sidewalk ramps on various streets in northern Yuma, roughly between Avenue A and 4th Avenue. Most of the major street reconstruction work is complete; however, work crews will continue to operate in isolated areas. The overall project is expected to conclude in summer 2024.
12th Street and Avenue C
In early April, the City will convert the intersection of 12th Street and Avenue C into a four-way stop, following pavement preservation work in the area. Motorists should watch for message boards and signs indicating the change.
Avenue 5E, 37th Street to 40th Street
A contractor working for the City is installing water and sewer lines on Avenue 5E between 37th Street and 40th Street, plus new fire hydrants and new service connections, followed by pavement replacement. Avenue 5E will be closed to through traffic between 32nd Street and 40th Street, and to all traffic between 37th Street and 40th Street. Detour using Avenue 4E or Avenue 6E. This project is expected to be complete in early spring.
45th Avenue, 24th Street to 28th Street
A contractor working for the City will construct a multi-use path along 45th Avenue between 24th Street and 28th Street. Most work will occur off the roadway; however, one phase of the project will prompt a closure of 45th Avenue between 24th Street and 26th Street. Project is expected to run through mid-April.
28th Drive, 31st Street to 29th Place
28th Drive traffic is restricted to northbound only between 31st Street and 29th Place for emergency storm drain repair.
Spring pavement preservation
Spring surface treatments are expected to run March 21 through the end of April. Impacted neighborhood property owners will receive a door hanger that indicates the area where the roadway maintenance is taking place as well as the dates and times. Find a complete list of roadways and subdivisions to be preserved on the Pavement Preservation page of the City's website. This page provides an interactive map where residents can zoom in on highlighted streets and click for that street's scheduled maintenance date.
March 25:
12th Street from Bardeaux Avenue to Haupt Avenue.
30th Ave from 12th Street to 13th Place.
28th Drive from 12th Place to 13th Place.
12th Lane from 28th Drive to end cul-de-sac.
12th Place from 30th Avenue to end cul-de-sac.
12th Lane from 30th Avenue to end cul-de-sac.
March 26:
12th Street from Haupt Avenue to Portal Drive.
12th Place from Haupt Avenue to end cul-de-sac.
13th Place from 30th Avenue to end cul-de-sac.
14th Street from 28th Drive to end cul-de-sac.
30th Avenue from 14th Street to 13th Place.
28th Drive from 14th Street to 13th Place.
Castle Dome Avenue from 8th Street to 9th Street.
March 27:
13th Place from 30th Avenue to Haupt Avenue.
12th Street from Avenue B to Portal Drive.
Castle Dome Avenue from 9th Street to 12th Street.
March 28:
Castle Dome Avenue from 12th Street to Yuma Palms Parkway.
16th Street from Avenue A to Avenue B.
March 29:
16th Street, westbound split.
March 30:
Walnut Avenue from 10th Street to 12th Street.
City Street Maintenance
City Street Maintenance operations for March 25-31 will take place in the following areas.
Streets Concrete Sidewalk Repair
Yuma Townsite.
College Park, unit 4.
Street Asphalt Patching
24th Street, 4th Avenue to Avenue A.
Arizona Avenue from 16th Street to 12th Street.
Avenue D from 8th Street to City end near Frances Street.
Streets Crack Sealing
16th Street from Avenue A to Avenue B.
Streets Lane Striping
24th Street from Avenue 5E to Avenue 6E.
24th Street and Avenue 9E intersection.
Arizona Avenue from 16th Street to 12th Street.
12th Street from Avenue C to Bardeaux Avenue.
Castle Dome Avenue from 8th Street to Yuma Palms Parkway.
16th Street from Avenue A to Avenue B.
Other utility projects and encroachment permits
Avenue A, Parkview to 28th Street (Yuma County)
A contractor working for Yuma County is working on the Smucker Park flood control basin, which will at times affect Avenue A between Parkview Loop and 28th Street. The sidewalk on the west side of Avenue A is closed. Motorists on Avenue A should be aware of trucks entering and exiting the roadway on the north side of the park. Later phases of work will include lane restrictions on Avenue A and a closure at Westridge, currently anticipated for early 2024. Message boards will be activated 72 hours prior to any such closure.
Fiber optic installations (Allo)
Communications line installations will take place in areas designated for utility easements within the City limits and surrounding vicinity in the following areas:
14th Avenue, Parkway Drive to Camino Real (Century Link)
Century Link has a 90-day project to replace a section of defective telephone cable. Part of this project will require the closure of 14th Avenue between Parkway Drive and Camino Real for an unknown number of days. Completion date is expected to be no later than April 5.
Avenue 8-1/2E, 34th Street to 40th Street (Gila Electronics)
Installation of new fiber optic cables will require a lane shift on southbound Avenue 8-1/2E between 34th Street and 40th Street through late April.
Maiden Lane, 1st Street to 2nd Street (Yuma County)
Installation of a construction crane will prompt the closure of Maiden Lane between 1st Street and 2nd Street.
Avenue B, 15th Street (Century Link)
Century Link has a 60-day project that will include a closure of the right southbound lane of Avenue B approaching 15th Street. Work is expected to conclude by mid-May.
24th Street, Pacific Avenue to Avenue 3E (SW Gas)
Gas line replacement work will include eastbound lane closures of 24th Street between Pacific Avenue and Avenue 3E. Work should complete in late April.