Water supply Project in Lh. Naifaru completed
Project contracted to Maldives Water and Sewerage Company (MWSC) have completed the Water supply Project in Lh. Naifaru. The testing and commissioning of the facilities were conducted from 19th July 202 to 22 July 2022.
Under this project, 2 Nos RO plant (100 ton each) and a water tank with the capacity of 1300 cubic meter was installed. And Water network have been installed for 1510 houses in Naifaru.
The project was contracted on 26th October, 2020 for MVR 13,136,034.10.