Transportation (Planning) 1/24/2020 North Nashville Bikeway Progress Update

1/24/2020

The following are some high points of North Nashville Bikeway Progress as requested:

Summary of work for January 20 through 24, 2020:

  • No striping installed this week due to temperatures below 50 and wet conditions.
  • Delineators approximately 75% complete on Ed Temple between Jefferson St and Buchanan St.
  • Corrective work on ramp on DB Todd at Wheless.
  • Met with Google for fiber relocation at DB Todd and Underwood prior to ramp work.

Two-Week look ahead:

  • Complete delineator installation on Ed Temple Blvd between Jefferson St and Buchanan St.
  • Striping to continue on Buchanan St/Garfield St and on Ed Temple at Jefferson St as weather allows (minimum temperature of 50 degrees and dry conditions).
  • Complete sign installation on Arthur Ave.
  • Concrete ramps and islands on Buchanan St at 11th Ave N & 14th Ave N, Garfield St at Delta Ave.
  • Google to start relocation of fiber at DB Todd and Underwood prior to ramp work.