Ohio Department of Transportation

04/18/2024 | Press release | Distributed by Public on 04/18/2024 23:58

Mahoning County: Construction update

April 18, 2024| ODOT

Week of April 22, 2024

Mahoning County (Thursday, April 18, 2024) - The following construction projects are anticipated to affect highways in Mahoning County next week. All scheduled work is weather permitting.

Interstate 76 noise wall, Milton Township
The ramp from I-76 westbound to SR 534 is closedthrough early May for noise wall construction. The detour is I-76 westbound to SR 225 to I-76 eastbound to SR 534.

Interstate 680 lighting improvements
I-680 at Midlothian Blvd. is reduced to two lanes through late April.Estimated completion, October 2024.

Interstate 680 resurfacing
I-680 northbound and southbound at Matthews Rd. is reduced to two lanes through May 2024 for bridge repairs. Estimated completion, October 2024.

US 224 culvert replacement, Poland Township
US 224 just west of Poland Way is closedthrough Friday evening, April 19. The detour is SR 616 to US 422 to PA I-376 to PA US 224.

State Route 165 resurfacing, Beaver & Springfield Townships
SR 165 between S. Range Rd. and the Columbiana County line has various lane restrictions. Estimated completion, late July 2024.

State Route 170 pavement reconstruction, Village of New Middletown & Springfield Township
CONTINUING IMPACT - Westbound E. Middletown Rd. to SR 170 will be closed through mid- May. A detour will be posted.
CONTINUING IMPACT- SR 170 southbound between Struthers Rd. and Middletown Rd. is closedthrough mid-October for roadway reconstruction. The detour is SR 617 to SR 165 to SR 626 to SR 7 to US 224 to SR 170. Estimated completion, October 2025.