U.S. 30 Work Continues at Millard and Bennett Roads Schedule Update
Our utility partner is working on relocating their line and should be completed soon. We anticipate installing our traffic control for the next stage of construction on Monday, September 27.
Work for this project is being done in stages as our contractor coordinates with our utility partners and the railroad contractor. Some of our work is dependent on our partners work. For this reason our schedule is subject to change.
Project area and detour route map.
Closure, Detour & Work Details
This stage of construction requires us to close Bennett Road on the west side of the U.S. 30 intersection. We will maintain at least one lane for southbound traffic on U.S. 30.
You can access Bennett Road from U.S. 30 by using Achilles Road or Church Road. The east side of Bennett Road will remain open.
During this stage we are:
Traffic Impacts
Work hours will vary and may be performed Monday through Friday, from 6 a.m. to 5 p.m. There may be nightwork needed.
Expect lane closures and delays.
Work Happening in 2022
The railroad contractor is upgrading the rail crossings at both intersections as part of the project. Some of the work we are doing needs to happen after the rail work is completed, including the final paving of the project area.
Visit the project webpage or TripCheck.com for the most recent information on closures and impacts.
Plan Ahead! Find out what's being built around the region. Check out our interactive construction map to see what projects are being built on the roads in communities around the Region. If your travels take you outside the region, TripCheck.com will have the most up to date information on road conditions and congestion. |