09/20/2021 | Press release | Distributed by Public on 09/20/2021 09:01

INT Planned Maintenance Shutdown Confirmation

Following the close of the stakeholder consultation that ran from 18 August to 17 September, Interconnector today confirms its maintenance plans for Gas Year 2021.

A maintenance shutdown will commence at 06:00 CET Tuesday 16 November for a period of 10 days ending at 06:00 CET Friday 26 November.

There will be no flow through the Interconnector in either direction for the duration of the maintenance period.

Media Release available here.