Toyota Motor Corporation

09/17/2021 | Press release | Distributed by Public on 09/17/2021 03:00

Adjustments to Domestic Production in October (as of September 17)

Sep. 17, 2021

Adjustments to Domestic Production in October (as of September 17)

Due to the parts shortage resulting from the spread of COVID-19 in Southeast Asia and other factors, we have announced on Sept. 10 our revised production plan for October (Adjustments to Domestic Production in August and September). We would like to announce today that there will be suspensions to domestic plant production for completed vehicles in Japan as follows.

We sincerely apologize for the inconvenience caused to our customers and suppliers due to these changes.

Production suspension in October (27 lines in 14 plants out of 28 lines in 14 plants)

Plants Period of production suspension Production vehicle
Toyota Motor Corporation
Motomachi Plant
Production line #1 1 (Fri), 8 (Fri), 15 (Fri) Crown, Noah, Voxy, Mirai
Production line for small vehicles C+pod
Production line for the Century Century
Production line for GR models GR Yaris
Production line for low volume models 1 (Fri), 4 (Mon), 5 (Tue), 8 (Fri),15 (Fri) LC
Toyota Motor Corporation
Takaoka Plant
Production line #1 1 (Fri), 7 (Thu), 8 (Fri), 14 (Thu),15 (Fri),21 (Thu),22 (Fri),28 (Thu),29 (Fri) Corolla / Corolla Touring,Corolla Cross
Production line #2 1 (Fri), 8 (Fri), 15 (Fri), 22 (Fri),29 (Fri) Harrier, RAV4
Toyota Motor Corporation
Tsutsumi Plant
Production line #1 1 (Fri), 8 (Fri), 15 (Fri) Prius, Prius PHV,Corolla
Production line #2 1 (Fri), 8 (Fri), 15 (Fri), 22 (Fri),29 (Fri) Corolla Sport, Camry, ES
Toyota Motor Corporation
Tahara Plant
Production line #1 1 (Fri), 8 (Fri), 15 (Fri) Land Cruiser Prado, GX, 4Runner
Production line #3 1 (Fri), 4 (Mon), 5 (Tue), 6 (Wed),7 (Thu),8 (Fri),11 (Mon),15 (Fri) LS, IS, RC, RC F, NX
Toyota Motor Kyushu
Miyata Plant
Production line #1 1 (Fri), 7 (Thu), 8 (Fri), 14 (Thu),15 (Fri),22 (Fri),29 (Fri) NX, CT, UX, UX300e
Production line #2 1 (Fri), 8 (Fri), 15 (Fri), 22 (Fri),29 (Fri) ES, RX
Toyota Motor East Japan
Iwate Plant
Production line #1 1 (Fri), 7 (Thu), 8 (Fri), 14 (Thu),15 (Fri),21 (Thu),22 (Fri),28 (Thu),29 (Fri) C-HR, Aqua
Production line #2 1 (Fri), 7 (Thu), 8 (Fri), 14 (Thu),15 (Fri),22 (Fri),29 (Fri) Yaris, Yaris Cross, Aqua
Toyota Motor East Japan
Miyagi Ohira Plant
Yaris Cross, Sienta, Corolla Axio,Corolla Fielder,JPN Taxi
Toyota Auto Body
Fujimatsu Plant
Production line #1 1 (Fri), 15 (Fri) Land Cruiser 70
Production line #2 1 (Fri), 8 (Fri), 15 (Fri), 22 (Fri),29 (Fri) Noah, Voxy, Esquire, Alphard
Toyota Auto Body
Inabe Plant
Production line #1 1 (Fri), 4 (Mon), 5 (Tue), 6 (Wed),7 (Thu),8 (Fri),15 (Fri),22 (Fri) Hiace, Granace, Alphard, Vellfire, LM
Toyota Auto Body
Yoshiwara Plant
Production line #1 1 (Fri), 4 (Mon), 5 (Tue), 6 (Wed),7 (Thu),8 (Fri),11 (Mon),12 (Tue), 13 (Wed),14 (Thu),15 (Fri) LX, Land Cruiser 300
Production line #2 1 (Fri), 8 (Fri), 15(Fri) Land Cruiser 70
Gifu Auto Body Production line #1 1 (Fri), 4 (Mon), 5 (Tue), 6 (Wed),7 (Thu),8 (Fri),15 (Fri),22 (Fri) Hiace / Ambulance
Production line #2 15 (Fri) Coaster
Toyota Industries Corporation Production line #301 1 (Fri), 8 (Fri), 15 (Fri) RAV4
Production line #302 RAV4, RAV4 PHV
Hino Motors, Ltd.
Hamura Plant
Production line #1 Land Cruiser Prado, FJ Cruiser
Daihatsu Motor Corporation
Kyoto (Oyamazaki) Plant
Probox
NotesLine #2 at Fujimatsu Plant, Toyota Auto Body operates at single shift.