IDGC of Centre and IDGC of Center and Volga region summed up the results of passing of the season of peak loads on the network and outlined the tasks for the 2017-2018гг

May 23, 2017 in Nizhny Novgorod held a press conference which summed up the results of passing companies to the autumn-winter period 2016-2017, the flood period of the current year and announced tasks in preparation for the season of peak loads on the network in the winter of 2017-2018.

Opening the press conference, first Deputy General Director - chief engineer of JSC IDGC of Centre, JSC, acting first Deputy General Director - chief engineer of JSC 'IDGC of Centre and Volga region' Alexander Pilyugin stressed that the past autumn-winter period (AWP) has demanded from Energetikov the maximum consolidation of power, increased efficiency and the implementation of a number of additional technical measures.

While weather conditions AWP 2016-2017 drastically differed from that recorded in the previous accounting period. In November 2016, branches, branch, Tverenergo and Vladimirenergo exposed to icy rain. The passage of the cyclone was accompanied by strong winds of up to 22 m/s with gusts of over 25 m/s, the sticking of wet snow, icing on the wires (to 29 mm), 'dancing' of wires. Under the weight of formed ice crusts trees growing outside the protective zones of power lines, began to lean to the wires, causing short circuits, and provoked the mass disconnection of customers.

Restoration of power supply of consumers in Kaluga region, which crossed the weather front width up to 60 km, caused serious damage to energy infrastructure, demanded a consolidation of forces and means of all branches of the two power companies. In the process and the results of elimination of technological disruptions energy drinks has additionally been cleared and extended the route of overhead power lines on the area of 503 ha.

A comprehensive analysis of the emergency situation and further developed and implemented technical measures would prevent the repetition of November events in the remaining winter months.

Also during the event with a presentation about the features of the autumn-winter period and preparation of the grid infrastructure in the region to the world Cup 2018 in Nizhny Novgorod region Deputy Director General - Director of branch 'Nizhnovenergo' Ivan Kleymenov. He noted that before the passage of the season's peak loads of energy to implement a range of activities in the region, including the execution of 105% of the repair program, 101% program of clearing and expansion of routes of overhead transmission lines (OTL), 108% - investment program.

In just the past year, the Nizhny Novgorod energy was completed a comprehensive renovation of the 35 substations (SS) of 35-110 kV, 2 179 of transformer substations of 6-10/0.4 kV and 8 776,65 km of transmission lines. In 2016 were cleared and extended 4 618 ha of overhead line routes. Another 120 ha of energy released from shoots in the first quarter of this year. Last year 'Nizhnovenergo' has commissioned 82,92 MVA of new capacity and 761,29 km of transmission lines. Construction and reconstruction was conducted on 3049 objects. In preparation for AWP 2017-2018 it is planned to put into operation 554 km of transmission lines and 87 MVA of transformer capacity, 38 repair of 35-110 kV substations, 2 176 TP 6-10/0,4 kV, 8 847 km of power transmission lines.

In parallel, the branch 'Nizhnovenergo' continues the implementation of complex of measures aimed at ensuring reliable and uninterrupted power supply in Nizhny Novgorod during the world Cup. The main works will be completed by the end of 2017. During the year the specialists of the company will renovate four substations (SS) 110 kV 'Kanavinskaya', 'Satellite', 'Kowaliw', 'the Manor'. In addition, in the framework of the implementation of the production program energy repairs 118 of transformer substations (TS) and distribution points (RP). In particular, it will be renovated facades of power, replaced the circuit breakers of 6-10 kV and 10,358 km of cable lines 6 kV (KL). To speed up the search places of the earth faults in networks of 6-10 kV and the time of elimination of technological violations in the six PS and 19 RP will be equipped with modern alarm device.

Concluding the press conference, Alexander Pilyugin said that currently the electric grid complex of 20 regions of Central and Volga Federal districts is actively preparing for the next autumn-winter period. This energy largely changed the approach to planning of production programmes based on the experience gained last winter. The maximum amount of work scheduled to be completed in September this year. The total amount of funding maintenance programs of the two companies for 2017 is 5 371 million. In 2017 a total energy company plans to renovate more 49.3 thousand km of overhead power lines 0.4-110 kV, and perform complex repair 393 substations (SS) of 35-110 kV.