03/01/2021 | Press release | Distributed by Public on 03/01/2021 16:43
COMMONWEALTH OF PENNSYLVANIA
Dept. of Environmental Protection
Commonwealth News Bureau
Room 308, Main Capitol Building
Harrisburg PA., 17120
On December 4, 2020, ETC submitted a revised PPC Plan that describes how the contents of the Revolution Pipeline would be removed in a safe and environmentally protective manner prior to permanent stabilization in the event of leak, release, or catastrophic incident like a landslide. ETC also demonstrated that all steep slope areas identified in the order currently meet the factor of safety DEP required.
DEP had previously documented numerous unstable slopes and numerous landslides have occurred along the pipeline right of way. Most notably on September 10, 2018, a landslide occurred along the Revolution Pipeline in Center Township, Beaver County that caused a break in a section of the pipeline that allowed methane gas to escape. The gas ignited, causing a fire that burned several acres of forested areas; destroyed a single-family home, a barn, and numerous vehicles; resulted in the evacuation of nearby residents; and caused six high voltage electric transmission towers to collapse.
ETC appealed DEP's November 2020 order to the Environmental Hearing Board. As required in the COA, ETC filed a stipulation of settlement with the Board and sent DEP notice that the pipeline would be placed into service as of March 1, 2021.
This COA includes corrective actions that ETC must undertake, including construction addressing drainage issues along steep slopes, submission of a revised permanent stabilization plan to provide for continuous stability monitoring of the 'Penny Hollow Site,' and daily monitoring of this site and immediate notification of land movement to DEP until continuous monitors are installed.
The $125,000 civil penalty will go into the Oil and Gas Program Fund.
###