CLERMONT COUNTY: Weekly Construction Update

Through the week ending April 20, 2024: The following traffic advisory includes restrictions on the state highway system in Clermont County. All work will be contingent upon the weather. For construction information and statewide information regarding road conditions, visit ODOT on the web at www.Ohgo.com.

EASTERN CORRIDOR PROJECTS

S.R. 32/Glen Este-Withamsville (GEW) Overpass - Construction of the GEW Road overpass bridge at the intersection with S.R. 32, as well as construction of a modified off-ramp from westbound S.R. 32 to GEW. The intersection has been closed to both north and southbound GEW Road, and traffic is being re-routed by way of the interchanges on S.R. 32 to the east and west. Traffic on S.R. 32 is being maintained through the work zone; however, intermittent lane restrictions may be in effect during hours of operations.

S.R. 32/Bach Buxton Interchange - Construction of an interchange at the intersection of S.R. 32 and Bach Buxton Road/Elick Lane and widening of S.R. 32 West between the new interchange and Glen Este-Withamsville (GEW) Road. All ramps of the new interchange are open to traffic, and the at-grade intersections between Old SR 74 and Glen Este-Withamsville Road have been closed. In addition to construction of a third, westbound lane on S.R. 32, finishing work, including signage and pavement markings, continues at the interchange.

S.R. 32 West Realignment - Realignment of westbound S.R. 32, between the Glen Este-Withamsville Road intersection and the I-275 interchange, to re-establish three, thru-lanes and realignment of the ramp from westbound S.R. 32 to southbound I-275. Intermittent lane restrictions may be in effect during evening and overnight hours.

NEW IMPACTS

S.R. 32 Pavement Repairs - From just east and west of the Bach Buxton Road interchange. Single-lane closures will be in effect in either direction on Tuesday, April 16, from approximately 9 a.m. to 3:30 p.m. Traffic will be maintained; however, motorists are advised of intermittent periods of delay throughout the day.

S.R. 132/222 Roundabout - At the routes' junction immediately north of S.R. 32. Preliminary operations are under way with retaining wall construction, and traffic is being maintained on both routes. Additional traffic impacts will be in effect throughout construction, and the entire project is scheduled for completion in the fall of 2024.

S.R. 133 Culvert Replacements - At two locations between Rudd Lane (north of S.R. 774 and the village of Felicity) and Mt. Olive-Point Isabel Road. Construction will start Monday, April 15, between Rudd Lane and Beech/Swope Road, and a 30-day closure will be in effect. This will be followed by a 30-day closure between Beech/Swope and Mt. Olive-Point Isabel roads. During periods of closure, traffic will be detoured by way of S.R. 756, S.R. 222, S.R. 232 and S.R. 125.

S.R. 133 Resurfacing - Between S.R. 32 at Williamsburg and S.R. 131, east of Newtonsville. Construction in the section between U.S. 50 and S.R. 131 will start Monday, April 15, and while traffic on northbound S.R. 133 will be maintained with the use of flaggers, southbound S.R. 133 motorists will be detoured by way of S.R. 131 and U.S. 50. The directional closure is anticipated to be in effect through mid-August. Through the remainder of the project, two-way traffic will be maintained by flaggers within the length of the entire work zone. The entire project is scheduled to be completed in late fall.

CONTINUING IMPACT

C.R. 171 (Old SR 74) Reconstruction - Between Schoolhouse Road and Springfield Court. Construction continues within the work zone; however, Old 74 is open between Dogwood Road and Elick Lane. Traffic will be maintained with the use of flaggers as needed during hours of operation. All associated work is scheduled to be completed in late summer or early fall of 2024.