Oxford flood scheme

Policy paper

Oxford flood scheme

How the Environment Agency plans to reduce flood risk in Oxford.

From:Environment AgencyPublished24 May 2018Last updated 15 April 2024 - See all updates
Get emails about this page

Documents

Details

The Environment Agency is working with partners on a major new scheme to reduce flood risk to homes and businesses in Oxford, as well as to services and major transport routes into the city.

Published 24 May 2018
Last updated 15 April 2024 + show all updates
  1. 15 April 2024

    Updated map of the scheme

  2. 22 March 2024

    Updated how the scheme will work, environmental vision, planning applications, Hinksey rail sidings, compulsory purchase order and find out more sections.

  3. 2 March 2023

    The Environment Agency have made a new compulsory purchase order (CPO) for the Oxford flood alleviation scheme. Updated information about 'What stage is the scheme at?'

  4. 31 March 2022

    Updated the section 'What stage is the scheme at'. The planning application has been submitted for Oxford Flood Alleviation Scheme.

  5. 17 May 2021

    Oxford Scheme update.

  6. 22 February 2021

    New collaboration with Earth Trust, to help get the best out of our long term plan for the environmental benefits of the scheme.

  7. 20 September 2019

    Updated application deadline to 31 October 2019.

  8. 9 July 2019

    We have added information about our Environmental Vision, including the advertisement for potential applicants.

  9. 17 April 2019

    Latest dates, updated map, plain English of the content

  10. 21 March 2019

    Updated texted 1) final planning decision now summer 2019. 2) Changed date to 2020 "If all approvals are granted construction will start in 2020 and is expected to take 3 to 4 years." 3) Added lines in the CPO section - "We have had confirmation from Defra that they intend to hold a Public Inquiry and a date is being confirmed for this. Due to the timeframes needed for this part of the process, the earliest construction of the scheme will start is in 2020."

  11. 28 January 2019

    Updated information on consultation.

  12. 21 December 2018

    Updated planning application section.

  13. 13 December 2018

    Added more information on compulsory purchase order, revised funding, and planning application.

  14. 3 December 2018

    Information on the planning application and partner websites.

  15. 26 September 2018

    Compulsory purchase order information added.

  16. 24 May 2018

    First published.