City of Manchester, NH

02/06/2023 | Press release | Distributed by Public on 02/06/2023 07:43

Christian Brook Sewer Separation Contract 1 - Week of February 6 - February 10

P. Gioioso & Sons will continue working in the streets during the week of February 6th thru February 10th.

Crew #1: Will resume excavation and installation of drainage pipe on Maple Street at the North Street intersection. Maple Street will be closed and all traffic will be detoured around the construction zone via Salmon Street to Hemlock Street.

Crew #2: Will not be on site this week.

Crew #3: Advanced Drilling and Blasting will continue drilling and blasting ledge on North Street from Oak Street to Hemlock Street.

In support of the project, Liberty Utilities and RH White will continue relocation of the gas main on Smyth Road.