Bridge Park Block G Construction Traffic Impact

The Block G section of Bridge Park is currently under construction. Here is what Dublin drivers should know when traveling through the area.

Traffic Impact:

Dale Drive will be closed from Bridge Park Avenue to Tuller Ridge Drive:

  • Tuesday, May 31, from 7 a.m. to 3 p.m.
  • Wednesday, June 1, from 7 a.m. to 5 p.m.
  • Thursday, June 2, from 7 a.m. to 3 p.m.
  • Friday, June 3, from 6:30 a.m. to noon

Mooney St. will have intermittent closures Monday - Friday for masonry work.

Work is expected to be completed October 2023. We thank residents and drivers for their patience.