Ohio Department of Transportation

04/18/2024 | Press release | Distributed by Public on 04/18/2024 11:56

Ashland County: Construction update

April 18, 2024| ODOT

ASHLAND COUNTY- (Thursday, April 18, 2024) -The following construction projects are anticipated to affect highways in Ashland County next week. All outlined work is weather permitting and is subject to change.

U.S. Route 42 & State Route 302 intersection improvement - The U.S. 42 and State Route 302 intersection will be converted from the current two-way stop-controlled intersection into a single lane roundabout.

NEW IMPACTS

  • SR 302 eastbound direction, from U.S. 42 to Township Rd 251/1080 intersection, will close Monday, April 22 to begin construction on the new roundabout. The intersection at U.S. 42 and SR 302 remains open, so motorists are able to travel along U.S. 42 during this phase of construction.
  • Access along SR 302 will be maintained for residents only. All residents and emergency personnel will need to enter the zone from SR 302 westbound.
  • This is phase one of the project and will approximately last from April 2024 till June 2024.
  • The detour route for all other motorists will be SR 302 west to SR 301 north to U.S. 224 west to SR 58 south to SR 302, and reverse.

Estimated completion of entire project: October 2024

State Route 89 & State Route 302 intersection improvement - The State Route 89 and State Route 302 intersection will be converted from the current two-way stop-controlled intersection into a single lane roundabout.

NEW IMPACTS

  • SR 302 eastbound direction, from SR 89 to U.S. 42 intersection, will close Monday, April 22 to begin construction on the new roundabout. The intersection at SR 89 and SR 302 remains open, so motorists are able to travel along SR 89 during this phase of construction.
  • Access along SR 302 will be maintained for residents only. All residents and emergency personnel will need to enter the zone from SR 302 westbound.
  • This is phase one of the project and will approximately last from April 2024 till June 2024.
  • The detour route for all other motorists will be SR 302 west to SR 301 north to U.S. 224 west to SR 58 south to SR 302, and reverse.

Estimated completion of entire project: October 2024