The project is progressing in line with international ESG standards, high quality and occupational safety policies. To date, 591,105 m3 of excavation and 104,390 m3 of backfill have been completed. A progress rate of 80% has been achieved in foundation pile works and 6.9% of concrete casting works have been completed. In addition, 14.6% of procurement packages has been committed and an overall progress rate of 7.41% has reached in the project.