05/09/2024 | Press release | Distributed by Public on 05/09/2024 15:50
Starting Monday, May 13, MG&E will replace their duct bank package on E. Doty Street in preparation for the continuation of the Doty Street & Wilson Street reconstruction project. During this time, E. Doty Street will be limited to one travel lane until August 16 when the closed lane will reopen and that portion of E. Doty street will be temporarily converted to two-way traffic lanes while the 100 Block of E. Wilson Street is fully closed to through traffic for reconstruction.
Reconstruction segment closure timeline:
Proposed work includes replacement of the asphalt pavement and road base, replacement of the sanitary sewer main and laterals, replacement of storm sewer, installation of new curb and gutter, and replacement of sidewalk and drive aprons as needed. This project is a continuation of the W. Wilson Street and Broom Street project completed in 2023.
Learn about any potential Metro Detours during these closures.