Ohio Department of Transportation

06/06/2024 | Press release | Distributed by Public on 06/06/2024 20:37

Wayne County: Construction update

June 06, 2024| ODOT

WAYNE COUNTY- (Thursday, June 6, 2024) - The following construction projects are anticipated to affect highways in Wayne County next week. All outlined work is weather permitting and is subject to change.

State Route 21 Major Rehabilitation - State Route 21, from the Stark and Summit County lines, will be reduced to one lane of traffic in each direction to reconstruct the roadway. Major work includes full-depth pavement replacement, bridge maintenance, culvert and drainage replacements, and safety improvements at four intersections along the project.

CONTINUING IMPACTS

  • Crews continue asphalt resurfacing along the southbound shoulder, starting from Eastern Road heading south. Pavement repairs in the right lane will follow after shoulder work is completed.
  • Signal timing at SR 21 and Edwards Road has been adjusted to increase green time for through lanes along SR 21; thus, helping to reduce delays at the intersection.
  • Crews will begin placing temporary pavement and paving crossovers in order to move all traffic onto the southbound lanes and close the northbound lanes.
  • Two lanes of northbound traffic and one lane of southbound traffic will be maintained.
  • Traffic will be maintained at Clinton, Edwards, and Eastern Road intersections, and right-turn movements will be maintained at Grill Road.

Estimated completion of entire project: June 2026

U.S. Route 30 resurfacing - NEW IMPACTS -U.S. 30, from the Ashland County line to the city of Wooster, will have single lane closures for a resurfacing project. An 11' lane will be maintained in each direction at all times. Estimated completion: October 2024State Route 83 Major Rehabilitation - State Route 83, from just south of U.S. 30 to Milltown Road, will have daily lane closures for final pavement repairs and resurfacing, striping, concrete median wall repairs, and miscellaneous finalization project work. Traffic will be maintained in one 11' lane in each direction at all times and traffic will be separated by portable concrete barrier wall.Estimated completion: June 2024State Route 94 double culvert replacement - State Route 94, between Doylestown Road and Eastern Road, is closed for a double culvert replacement. The detour route will be SR 94 north to SR 585 south to SR 57 north to I-76 east to SR 94, and reverse. Estimated completion: Friday, June 14, 2024U.S. 250 bridge replacement -U.S. 250, between Honeytown Road and E Messner Road, will have single lane closures for a bridge replacement project. Traffic will be maintained by temporary traffic signals. Estimated completion: October 2024State Route 585 resurfacing -State Route 585, from just west of SR 57 to SR 604, will have single lane closures for a resurfacing project. Traffic will be maintained at all times utilizing flaggers. Estimated completion: September 2024

Sign up for email updatesor follow the Ohio Department of Transportation (ODOT) District 3 on Facebookor Twitterfor current Wayne County highway construction information.