City of League City, TX

04/18/2024 | News release | Distributed by Public on 04/18/2024 14:13

Park Projects Updates

Did you know that League City has 15 City Parks, 2 Dog Parks and 24 miles of Hike & Bike Trails? There is also a host of other amenities available to our citizens such as paddle trails, granite walking/running trails and a mountain bike course.

The Project Management group works in conjunction with the Parks Department to design and construct these amenities and renovate them when they have reached the end of their useful life. We are currently working on eight projects in varying stages of design or construction. Below are a few highlights from our on-going projects.

To learn more about projects that impact your neighborhood, explore our interactive project map here

Construction

Lynn Gripon Park Low-Water Crossing

https://www.leaguecitytx.gov/4217/Lynn-Gripon-Park-at-Countryside-Mountain

The low-water crossing at Magnolia Creek will allow access east of the creek to develop and maintain phase 2 of the mountain bike trail as a continuation of phase 1 that opened in fall of 2021. To avoid encroachment into wetlands, the consultant completed a wetland delineation for the area east of Magnolia Creek for the future development of phase 2 of the mountain bike trail. The project consists of three 11'x11' box culverts crossing Magnolia Creek east of Lynn Gripon Park, cast-in-place wingwalls and headwalls, concrete pavement section for trail crossing, and grading around the crossing location.

The contractor mobilized in December. Temporary fencing has been installed in the dog park to enclose construction equipment and preclude access from the remainder of the park. Clearing and construction activities started in February. As of Monday this week, all of the box culverts have been installed and the contractor is working on the wingwall connections which are expected to be installed on April 19. Over the next month they will be working to install handrails, continue with the clearing and desnagging efforts along the creek, work on site grading and start restoration activities. They are on schedule to meet their completion target in early May.

Design

New Projects for FY 24 - Newport Park Redevelopment, Lobit Park and the East Side Dog Park Parking Access

As our FY24 CIP projects are ramping up, we have three new Park projects starting which include Newport Park Redevelopment, Lobit Park and the East Side Dog Park Parking Access.

The approximately 9-acre Newport Park site serves as a neighborhood park with an existing playground, trails, a basketball court, a baseball backstop and a parking lot. The Homeowners Association (HOA) park was conveyed to the city in 2005. One of the city's strategic goals is to provide quality amenities. The addition of a trail system within the park, improvement to the existing parking lot lighting, regrading of the open practice field, and adding a volleyball court will address the needs of the residents for this park. A professional services agreement for design went before and was approved by Council at the February 13th meeting.

Lobit Park was a Galveston County Park until the City took it over in February 2022. The park currently consists of an outdoor pavilion, restrooms, baseball field, basketball court, soccer fields, parking lot, a tennis court slab, and a former volleyball court area. Lobit Park went through a Condition Assessment in September 2020, as well as an Updated Condition Assessment in June 2021. These assessments provided some projected costs to get the park and associated facilities repaired and safely reopened. Design of Phase 1 is planned to be completed in 2024 with construction taking place in 2025. Halff Associates design contract was approved via Council action on March 26th. Phase 2 will be designed and completed in the future.

The east side dog park (Hometown Heroes Park Dog Park) was completed in 2023. Alternative access from FM270, via the Centerpoint Energy Easement, will allow users a closer access to the dog park and separate from the 5K Loop users. The concrete access with 20 stall parking, pedestrian crossing, and gate will be open during daylight hours. The design will include a survey, geotech, civil, landscape, irrigation, TXDOT coordination, and construction documents for bid and construction phases. The design proposal was presented for Council consideration at the April 9th meeting and was approved. The notice to proceed for the consultant to start design is April 22, 2024, with a design duration of 205 days. Design of the parking access is forecasted to be complete by November 2024. Construction is anticipated to start in the first quarter of 2025.

Bay Colony Park (PK2001)

https://www.leaguecitytx.gov/4350/Bay-Colony-Park

The proposed Bay Colony Park is located on Ervin Street west of Calder Rd. It is approximately 106 acres and is being designed to include a 5-field girls softball complex, a 4-field Pony-Colt baseball complex, 2 soccer fields, 2 playgrounds, a 5K Trail, a 9-hole disc golf course, tennis/pickleball courts, lighted parking and roads, restrooms, concession stands, detention ponds, irrigation, landscaping, and a maintenance facility.

The 60% Construction Document submittal was received from the consultant in late September 2023. Plans for an entrance into the east side of the park from Calder Drive are being developed but are delayed due to negotiations with the landowner. Metes and Bounds for that entrance road have been received as well as a title insurance commitment. An appraisal was recently provided; it is necessary to begin the acquisition process for the ROW needed for the road. This entrance will supplement the two entries into the north part of the park from Ervin Street, providing better ingress and egress from the park, during ball games and other large, heavily attended events. A right turn lane will be required into the eastern entrance off Ervin Street to reduce congestion on Ervin Street. Remediation work is now being studied by the Texas Railroad Commission (TRRC) under the EPA's Brownfields Program. By the end of August 2024, the TRRC will carry out any required remediation on the site. Construction Documents are scheduled to be complete and reviewed by COLC by the fall of 2024. The TPWD Outdoor Grant was not recommended for approval by the Texas Parks and Wildlife Commission when they met on January 25th.

The Grand Parkway alignment through the southern part of the park shifted north about 27' but is not expected to affect the recreational uses of the park but some detention ponds will be redesigned. A large portion of the park's detention is to be constructed on land south of the Grand Parkway; no recreational facilities will be constructed south of the Grand Parkway/Highway 99 corridor.

The City is working with the park design consultant and Phillips 66 to coordinate changes to an underground pressurized line owned by Phillips 66. The work on the line by Phillips 66 is expected to be carried out during the summer, prior to any construction work on the park. Phillips 66 and the City are still working on the details of the pipeline work that will affect the park facilities and vice versa.


FM 270 Public Boat Ramp Renovations

https://www.leaguecitytx.gov/4348/FM-270-Public-Boat-Ramp-Renovations

This project will renovate the existing FM 270 Public Boat Ramp to accommodate all forms of boats and watercraft. The renovation will remove silt from the launch area, repair damaged launch surfaces, and reinforce the bulkhead, which is at the end of its life. The parking lot will be repaired and expanded if funds allow.

The U.S. Army Corps of Engineers Permit was approved in the Spring of 2022. Final design plans were signed off on by the City in February 2023. Approved plans were sent to Texas Parks & Wildlife Department (TPWD) as well in February and then to then US Fish & Wildlife Service (USFWS) for review and approval for grant funding. TPWD forwarded the plans to USFWS in March 2023 to continue the review process. In April, TPWD forwarded comments from USFWS which were sent to the consultant. Responses to those comments were forwarded to TPWD and USFWS.

Staff communicated the city's concern over the long delay by USFWS for approval of the construction plans. TPWD replied with a detailed list of actions that must be completed with an uncertain but expected completion date of June 2024 to get to Bidding and Construction. Recently, TPWD was contacted to determine why USFWS's FONSI was delayed. The new director of the Boating Access Grant Program has listed documents that the City must provide in order for USFWS to issue the FONSI.

An extension of the TxDOT Multiple Use Agreement (MUA) has been approved and was received on February 12th by COLC from TxDOT. Bidding will follow the necessary approvals and construction is expected to take 9 to 10 months with the boat ramp being closed during that period.

Clear Creek - Nature Center & Kansas St Kayak Launch Sites

The purpose of this project is to design and construct 2 kayak launches, one at the end of Kansas Ave and another within the Dr. Ned and Fay Dudney Clear Creek Nature Center (the Nature Center), on the west side of Highway 270 and at the south end of and immediately west of the loop road that provides access to the boat ramp. The current design includes parking, ramps, and other required access to the launches, handicapped accessible launch platforms at each location, wayfinding signage, removal of abandoned improvements along the shoreline at the Kansas Street site, and restorations of shoreline marsh conditions at the Nature Center site. Other amenities such as picnic facilities will be considered if the budget allows.

Due to wetland conditions at the Nature Center site, an elevated boardwalk will be required to access the kayak launch at the water's edge. A Phase 2 Environmental Site Assessment was conducted on the Kansas Avenue site due to undocumented fill operations in the past.

Early stages of the Nature Center design were delayed by environmental and archeological issues. The Nature Center proposed launch site was relocated to avoid impacting a Native American archeological site. The USACE Permit application was received by USACE on 10/2/23. The 90% submittal review was returned to Burditt on 11/29/23. 90% Plans were submitted to TxDOT 12/8/23 for a preliminary review. TxDOT requires submission of a City Council resolution, a proof of insurance form, and a full application for the MUA. An additional delay might occur if TxDOT requires changes to the plans within TxDOT ROW. The consultant is currently preparing the "final plan" submittal, which is expected in March. Staff and consultants will review the plan which currently has an excess of fill due to the design of the parking area. The project needs to maintain a balance of cut and fill because of its location in the floodway.

Geotech borings and topographic survey are complete on the Kansas St site. Partial 30% documents provided prior to the complete 30% submittal allowed city planning and engineering departments a preliminary review of cul-de-sac size. 30% Submittal review comments were sent to Burditt on November 2023. 60% design plans were submitted at the end of December 2023. Comments were returned in early February. The 90% submittal should be received by the end of March.

The city is coordinating the kayak launch plans at the Kansas St site with the kayak launch consultant and the consultant for the proposed shoreline trail within the Kilgore-Davis Tract, north of the Dallas Salmon Wastewater Treatment Plant. The shoreline trail will connect the kayak launch with Heritage Park, via a series of ground level trail segments and elevated boardwalks with viewing areas along Clear Creek.

Gilmore Elementary-Claremont Trail

https://www.leaguecitytx.gov/4383/Gilmore-ElementaryClaremont-Connector-Tr

The Gilmore Elementary-Claremont Trail connection will connect to and become a part of the City's trail system as well as provide new sidewalks and a pedestrian bridge as a safe route from existing trails north of Gilmore Elementary School. The trail will cross a detention/drainage area adjacent to the school. After reviewing alternate layouts, the City chose the option that is anticipated to be the most cost effective, as well as a more direct route for end users, and a shorter bridge span. Final design plans have been approved. Acquisition of easements is in progress. Magnolia Creek HOA has agreed to grant the revised trail easement needed. Documents are being revised and reviewed through the legal department. The project advertised for bid on April 9th and the bid opening is scheduled for May 6th. It is anticipated the construction contract will be awarded at the last meeting in May and construction can start in June 2024.

Hike and Bike Trails Wayfinding Signage Project Phase 2

https://www.leaguecitytx.gov/4382/Hike-Bike-Way-Finding-Signage-Project-Ph

The City of League City has developed a family of hike and bike trail wayfinding signage which includes four different sign types. The first phase of signage was installed in 2021 within the Feathered Friends Trail System and included directional signs, park signs, and informational signs. Phase 2 is anticipated to incorporate 29 new signs within the Flora and Flowers Trail System, 20 signs within the Coastal Creatures Trail System, as well as installing an additional four signs within the Phase 1 trails, totaling 53 new signs. Final sign placements have been determined and trail and segment names for the Flora and Flowers Trail System and the Coastal Creatures Trail System have been sent to the consultant. 90% design plans were submitted in mid-November, and comments have been returned. Consultant has finalized the graphics and signage locations. Revised plans were submitted in April 2024.

Master Planning/Studies

Heritage Signature Trail Layout

https://www.leaguecitytx.gov/4541/46002/Heritage-Signature-Trail

A public meeting was held on March 7, 2023 at Butler's Courtyard for City staff and consultants to explain this project in some detail to residents of the historical district. This study looked at possible routes to connect League Park and Heritage Park through the Historical District. The consultant shared maps of possible walking and interpretive pathways to allow residents and visitors a way to see more of what League City has to offer. The presentation from the public meeting is available on the city website. Staff used conceptual schematics for a request to Union Pacific railroad to place the trail in their ROW-the alignment most preferred by residents attending the public meeting. However, Union Pacific has denied the city permission to locate the trail within their right-of-way. The city is considering some other layout options and is looking at other routes through the neighborhood. In December 2023, the city's consultant on the earlier study provided a proposal for an Add Service to the current PSA for the Trail Project. The amendment covering the new work will take the project through design of a new alignment and meeting with the public in a community meeting and was approved the week of January 22nd. Halff has developed 3 alignment options after a discussion with staff. Those will be evaluated by staff and discussed with Halff, with one or all 3 concepts presented to the public in a meeting in the next month or so.

Parks, Trails, and Open Space Master Plan Update

The City of League City Parks, Trails, and Open Space Master Plan (Master Plan) was approved in 2017 but must be updated every 5 years to be viable for use in Texas Parks and Wildlife Department (TPWD) park grant applications. A scientifically valid random survey of residents has been conducted and the City's consultant has reviewed the information and included their findings and recommendations in a draft of a new chapter for the Master Plan that will determine Park and Recreation priorities for the next 5 years. The Master Plan update will include a new chapter on changes since 2017 as well as the new chapter on Mountain Bikes approved in 2022. The City's consultant's work on the additional chapter will summarize the updates from the original masterplan. An extension of the contract in 2023 was approved due to the length of time required to access census information for the city. Completion of the update is expected by early summer 2024. That will make the update available for use in any grant applications later in the year. The consultant provided the master plan chapter draft on December 15th. The master plan review by city staff was completed by January 31st.

A Public meeting was held on February 20, 2024 from 6:00 PM - 7:30 PM at the Johnny Arolfo Civic Center located at 400 West Walker, League City, TX 77573. Comments from Public Meeting have been incorporated into the latest draft, which was presented at the March 18th Parks Board Meeting. The plan was approved at the April 15th Parks Board meeting and is scheduled for an upcoming work session with Council.

Kilgore Tract Preliminary Assessment

The City of League City is exploring the feasibility of developing a connecting trail and boardwalk between Heritage Park and the future Kayak Launch at Kansas Street, within a site known as the Kilgore Tract. The site will provide views of the Clear Creek environment as well as an approximately 3000 linear foot walking trail and elevated boardwalk.

Environmental, Archeological, and Wetland studies were previously conducted by the City's consultant on this project. The results of the studies show that no Phase 2 Environmental Assessment is required, and the Wetland delineation revealed that trail and boardwalk access to the shoreline of the site is feasible with a US Army Corps of Engineers (USACE) Nationwide Permit.

A meeting was held with the consultant in December 2023. A professional services agreement for the complete design of the shoreline trail has been negotiated and is anticipated to go before Council for approval in April 2024. Design is currently planned for FY2024 through FY2025 with construction beginning in FY2026.

The trail preliminary configuration is outlined in red on the site plan below from the Clear Creek Master Plan, approved by City Council in 2024.