Project Update | May 7

American Tobacco District Waterline Replacement - Phase 1 Project Update and Two-Week Look Ahead

May 7, 2021

The City appreciates your ongoing patience with the work along the busy corridors associated with this project. Additional information regarding this project can be found at: https://durhamnc.gov/2780/American-Tobacco-District-Waterline-Repl.

Planned Road / Lane Closures will occur as follows:

  • Week of 5/10:
    • Temporary lane closures of Jackson Street east of Willard Street.
    • Full closure of Jackson Street between Duke Street and Willard Street.
    • Lane closure in Duke Street between Yancey Street and Pettigrew Street.
  • Week of 5/17:
    • Temporary lane closures of Jackson Street east of Willard Street.
    • Full closure of Jackson Street between Duke Street and Willard Street.
    • Lane closure in Duke Street between Yancey Street and Pettigrew Street.

Saturday - Sunday May 8-9, 2021:

  • No work will take place on Saturday or Sunday.

Week of May 10, 2021:

  • Jackson Street east of Willard Street will have temporary lane closures to accommodate waterline installation.
    • Traffic control signs and markings will be used for the Jackson Street detour.
    • Access to the ATC North Deck via Willard / Julian Carr will be open during lane closure.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Planned water service interruptions will be coordinated at least 7 days in advance.
  • Jackson Street between Duke Street and Willard Street will have a full closure to accommodate transmission main installation.
    • Traffic control signs and markings will be used for the Jackson Street detour.
    • Access to the parking deck and surface parking lot will be maintained.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Duke Street between Yancey Street and Pettigrew Street will have a lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the lane closure.
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

Saturday - Sunday May 15-16, 2021:

  • No work will take place on Saturday or Sunday.

Week of May 17, 2021:

  • Jackson Street east of Willard Street will have temporary lane closures to accommodate waterline installation.
    • Traffic control signs and markings will be used for the Jackson Street detour.
    • Access to the ATC North Deck via Willard / Julian Carr will be open during lane closure.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • Planned water service interruptions will be coordinated at least 7 days in advance.
  • Jackson Street between Duke Street and Willard Street will have a full closure to accommodate transmission main installation.
    • Traffic control signs and markings will be used for the Jackson Street detour.
    • Access to the parking deck and surface parking lot will be maintained.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.
  • Duke Street between Yancey Street and Pettigrew Street will have a lane closure to accommodate waterline installation.
    • Traffic control signs and markings will be used for the lane closure.
    • Lane shifts with flaggers will be utilized for traffic control while work is taking place in intersections and at waterline connection locations.
    • Sidewalk traffic will be disrupted.
    • Noise levels in excess of the current City noise ordinance are anticipated during work hours.
    • Planned work hours are 7 AM to 7 PM.
    • No water or sewer service disruptions are anticipated.

Saturday - Sunday May 22-23, 2021:

  • No work will take place on Saturday or Sunday.

If you have questions, please email [email protected].