Construction Update- South Hill Terrace

Construction Update- 100 Block South Hill Terrace

PROJECT NAME: Water and Sewer Service Installation

PROJECT LOCATION: 123 South Hill Terrace

PROJECT DESCRIPTION: Crews will install a new water and sanitary sewer service.

START DATE: Thursday, June 1st at 7:00am

COMPLETION DATE: Friday, June 2nd at 3:30pm

LOCAL IMPACTS: The 100 Block of South Hill Terrace (one-way section) past the intersection of Hillview Place will be closed to through traffic during work hours (7am-3:30pm).

RECOMMENDED DETOURS: None posted

INTERRUPTIONS TO WATER SERVICE: None

For additional information contact: Nick Thomas, Jamie Lauper, or Rodney Vaow, DPW, Water & Sewer Division (607) 272-1717