Diaphragm wall and barette pile installation works at the Phase 1 of the Nador Port Project were completed by ENKA's subsidiary Kasktaş as of May 12, 2021. The main contractor has already started installation of tie-rods and concrete works at the Phase 1 and all works are expected to be completed in June 2021. All remaining works within the scope of the project are planned to be completed by the end of September 2021.