Huron County: Construction update

April 25, 2024| ODOT

HURON COUNTY- (Thursday, April 25, 2024) -The following construction projects are anticipated to affect highways in Huron County next week. All outlined work is weather permitting and is subject to change.

State Route 13 reconstruction - State Route 13, from the Richland County line to U.S. 250, will have single lane closures for a minor reconstruction project. Project work includes pavement replacement, culvert repairs, and bridge maintenance work.

NEW IMPACTS

  • SR 13, from U.S. 224 to SR 162, will close Monday, May 6 for 200 days so crews can complete pavement reconstruction work. Only local traffic will be maintained on SR 13. The detour route will be SR 13 north to U.S. 224 east to U.S. 250 west to SR 162 west to SR 13, and reverse. Estimated completion: Friday, November 22, 2024

Estimated completion: June 2025

State Route 61 culvert replacement - State Route 61, between Egypt Road and W Townline Road, will have single lane closures for a culvert replacement. Traffic will be maintained at all times utilizing flaggers when necessary. Estimated completion: June 2024State Route 99 Major Rehabilitation - State Route 99 reconstruction from SR 103 to U.S. 20.Work includes pavement edge reconstruction, pavement repairs, and asphalt resurfacing completed over three construction phases.

CONTINUING IMPACTS

  • SR 99, from SR 103 to SR 162, is closed for pavement reconstruction work. This phase of the project is estimated to be completed in May 2024.
  • The detour route is SR 99 north to SR 103 east to SR 61 north to SR 162 west to SR 99, and reverse.
  • Access is only maintained for residents.

Completion of entire project: October 2024

State Route 99 culvert replacement -State Route 99, between Mead Road and Webb-Settlement Road, is closed for 30 days for a culvert replacement. There will be two posted detour routes:
  • Northbound Detour: SR 99 north to U.S. 20 west to SR 4 north to SR 99, and reverse.
  • Southbound Detour: SR 99 south to SR 113 west to SR 4 south to U.S. 20 east to SR 99, and reverse.

Estimated completion: May 9, 2024

U.S. Route 224 bridge repairs -U.S. 224, between Lane Road and Greenwich Milan Townline Road, will be reduced to one lane of traffic for a bridge repair project. Traffic will be maintained by a temporary traffic signal. Estimated completion: June 2024U.S. Route 224 resurfacing - NEW IMPACTS -U.S. 224 from the Seneca County line to the Ashland County line, outside the city of Willard corporation limits, will have lane closures for a resurfacing project. Traffic will be maintained at all times. Estimated completion: September 2024U.S. Route 250 railroad repairs - NEW IMPACTS -U.S. 250 in the city of Norwalk, just south of Water Street, will close Monday, May 6 for Wheeling Lake Erie Railroad crossing repairs. The detour route will be U.S. 250 west to U.S. 20 east to SR 601 north to SR 113 west to U.S. 250, and reverse. Estimated completion: Wednesday, May 8, 2024