As the city of Aurora improves its infrastructure offerings to its current and future residents, demands for more infrastructure, improvements and repairs also grow. On any given work day, there can be as many as 100 active work zones within the city.
Traffic engineering staff do make an effort to minimize the impact of these work zones to the traveling public. In addition to reviewing and approving the plans to ensure they are safe and compliant with all regulations, staff also work with contractors to seek alternatives to street closures and minimize the number of lane closures and their duration. Staff also try to keep conflicting work zones from overlapping in time or space. In most cases, these efforts are successful. However, on occasion, alternatives are not available and since we are dealing with the outdoor environment, even the best planned projects get delayed by weather, special events or unknown conditions, resulting in confusion and/or unplanned congestion.
Sign up now for weekly construction updates delivered directly to your inbox via Road Construction Roundup.
The 2024 road construction projects map is now posted. See the Weekly Roadwork Construction Schedule
Visit this linkfor more information about city of Aurora roadwork.
In-progress Projects
I-70 full closure
Both directions of I-70 between Tower Road and Colfax Avenue will be fully closed overnight May 13 (8 p.m. to 5 a.m. westbound and 10 p.m. to 5 a.m. eastbound) to complete work on the new High Line Canal Trail pedestrian bridge over the interstate. Follow the signed detour route, which will use Colfax Avenue between Tower Road and Gun Club Road. Expect slow traffic.
The right shoulders on both east- and westbound I-70 between mile markers 287 and 288 will be closed for the foreseeable future.
Please be alert: Don't follow trucks into the work zone. Trucks will be exiting off eastbound I-70 and directly into a temporary work zone west of Colfax Avenue (Exit 288). Slowing to below 45 m.p.h. near the railroad bridge east of the Tower Road interchange, they will then exit onto the shoulder to enter the work area.
For more information on this project, visit the project webpage or sign up for weekly updates.
Havana and Mississippi lane closures
An Xcel Energy project to perform gas line maintenance will affect both directions of Havana Street at Mississippi Avenue, resulting in multiple lanes being closed from 7 p.m. to 7 a.m. daily from May 20 to July 3. Use alternate routes; plan for delays. All left turns will be prohibited. Bypass route for avoiding this intersection is to use Peoria, Dayton, Alameda or Jewell.
Northbound Chambers partial and full closures between Colfax and Smith
A private development project affecting northbound Chambers Road between Colfax Avenue and Smith Road will have one or more lanes closed from May 20 to June 5 to maintain infrastructure. Use alternate routes. This same stretch of road will have a full closure from May 24 to 31 for the same reason. Follow the signed detour, which will use Airport Road between Colfax Avenue and Smith Road. A full closure also is planned in this area from Aug. 2 to 9 for additional work.
Northbound Chambers full closure between Sixth and Colfax
A private development project affecting northbound Chambers Road between Sixth and Colfax avenues will result in a full closure from May 29 to June 5. Follow the signed detour, which will use Airport Road between Sixth and Colfax avenues. This same closure also will occur from Aug. 7 to 14.
Southbound Chambers turn lane closure at Hinkley
A private development project affecting southbound Chambers Road at Hinkley High School will close a left turn lane from May 29 to June 5. Use alternate routes. Entrance and exit for Hinkley High School will be closed to and from Chambers Road. This same closure also will occur from Aug. 7 to 14.
Southbound Chambers lane closures at Sand Creek
A private development project will close two lanes on southbound Chambers Road from June 3 to 13. Use alternate routes. This same closure also will occur from Aug. 12 to 19.
Metro Water Recovery project may result in short-term road closures
As part of ongoing and routine wastewater treatment system maintenance, Metro Water Recovery is rehabilitating segments of corroded pipe within Aurora. The Aurora Westside Interceptor Rehabilitation Project is necessary to maintain about 23,000 feet of pipeline that runs from Parker Road and I-225 to Dayton Street and Smith Road.
The work performed by Inliner Solutions began in early September. Construction for this critical infrastructure will be limited to brief disturbances at 11 bypass locations. Short-term road closures and/or traffic detours may be needed along bypass pumping routes.
Affected locations in 2024 may be viewed on the project website.
CDOT Road Construction Updates
View weekly construction updatesfrom the Colorado Department of Transportation.
E-470 Road Widening Updates
View more on this project from the E-470 Tollway Authority.
East Colfax Bus Rapid Transit
The city and county of Denver, in partnership with RTD, the city of Aurora and CDOT, is moving forward with Bus Rapid Transit (BRT) on East Colfax Avenue. This project is intended to move more people more efficiently and more safely along the Colfax Corridor.
Based on available funding, construction is slated to begin in late-2024, with the system operating starting in 2027. Buses will run down center transit lanes in Denver and on side-running transit lanes in Aurora. The city of Aurora negotiated an intergovernmental agreement with Denver to fund the design and construction of BRT elements along the Aurora portion of Colfax.
For more information on the project, visit DenverGov.org/ColfaxBRT.
Aurora Water Retweeted Aurora Water
TRAFFIC: Due to unforeseen circumstances, detours will remain in place on n-bound Gun Club Rd through the pm rush hour & into the evening for work at this site. We'll also need to continue work tmrrow, so detours will be in effect from 8:30am-mid afternoon.
Aurora Water Retweeted Aurora Water
TRAFFIC: Due to unforeseen circumstances, detours will remain in place on n-bound Gun Club Rd through the pm rush hour & into the evening for work at this site. We'll also need to continue work tmrrow, so detours will be in effect from 8:30am-mid afternoon.