10/06/2022 | Press release | Distributed by Public on 10/06/2022 10:09
The end of the tunnel after 7 years of work! Congratulations to our teams who have completed one of the first major projects of the Lyon-Turin project !
The numbers are staggering :
500 people on peak shifts
24 hours a day
7 days a week
52,416 segments
600 m deep
9 km of tunnelling
3 km of digging using traditional methods
Relive the major stages of this work on video !
Did you know ? The objective of the SMP4 project was to excavate the most critical zone of the route and to validate the overall feasibility of the project. In the "productive coal mine", a very heterogeneous geological zone, convergent (1 m in diameter) and under great cover (600 m deep), the teams managed to excavate 9 km with a tunnel boring machine and 3 km using the traditional method, in mechanical or explosive mode, in complete safety.
Consortium: Eiffage Génie Civil, Spie batignolles, Ghella, CMC di Ravenna, COGEIS SPA
Client: TELT Lyon Turin