Navy Shipbuilding: Increased Use of Leading Design Practices Could Improve Timeliness of Deliveries

Why This Matters

Changing maritime threats are pushing the U.S. Navy to increase its pace for designing and delivering new ships. Since 2009, GAO has used leading practices in commercial shipbuilding to evaluate the plans and execution of Navy shipbuilding programs. GAO's numerous recommendations have spurred Navy action to improve acquisition practices and the use of taxpayer dollars. Yet, the Navy has continued to face persistent challenges in its ability to design and deliver timely, affordable new ships that perform as expected.

Computing power and digital design capabilities have rapidly changed in the 15 years since GAO first identified leading ship design practices. As a result, GAO's examination of commercial industry's current practices helps ensure that the activities and performance of the Navy's shipbuilding programs are evaluated against cutting-edge practices used to design new ships efficiently and effectively.

Key Takeaways

GAO found that leading commercial ship buyers and builders prioritize shorter, predictable periods for design and construction, which result in delivering timely ships that meet current user needs. In contrast, the Navy's approach often results in significantly longer design and construction cycle times for its shipbuilding programs' lead ships.

Comparison of Design and Construction Cycles for Selected Commercial and Navy Ships

Note: For commercial ships, the range of months indicates the shortest and longest typical periods for companies to deliver a ship after contract award. For Navy ships, the range of months for different ship types indicates the shortest and longest periods for the Navy to provide selected lead ships to the fleet since 2007. For Navy programs with a contract prior to the detail design and construction award, the earlier award date represents the start of the cycle.

Key differences between commercial companies' and the Navy's ship design practices contribute to the slower pace and less predictable cost, schedule, and performance outcomes for Navy shipbuilding programs. Leading design practices involve

  • effective management of a ship's business case-a reflection of the balance of customer needs and the resources needed to develop and produce the ship; and
  • focus on efficiently maturing new ship designs to better inform decisions on schedule, cost, and performance. This includes using consistent, meaningful design maturity measures to determine readiness to move from design to construction.

GAO Comparison of Leading Ship Design Practices for Commercial Companies and U.S. Navy

How GAO Did This Study

A conference report directed GAO to examine ship design practices. This report assesses (1) the leading design practices used by commercial ship buyers and builders to inform their understanding of design maturity and readiness for construction, and (2) how the Navy's ship design practices compare to the leading practices in commercial ship design. To address these objectives. GAO interviewed and reviewed documentation from four commercial ship buyers and five shipbuilders-builders generally also design the ships. GAO selected these companies using criteria reflective of commercial success in designing, building, and buying ships relatable to Navy ships. GAO also reviewed its prior work on leading practices for shipbuilding and product development. In addition, GAO reviewed documentation and interviewed representatives from the Navy and selected Navy shipbuilders, as well as reviewed prior work on Navy shipbuilding program efforts. Based on the results of these activities, GAO compared the ship design practices used by the Navy with leading commercial practices.