City of Palo Alto, CA

03/29/2024 | Press release | Distributed by Public on 03/29/2024 18:18

El Camino Real Construction Impacts Update

El Camino Real Construction Impacts Update

Published on March 29, 2024

Construction activity along El Camino Real and near several cross streets will continue to impact vehicular traffic, and the public should anticipate bicycle and pedestrian impacts as well. Please consider alternative routes in early April.

SFPUC Pipeline Inspection Project

The San Francisco Public Utilities Commission (SFPUC) will be conducting an inspection of one of their drinking water transmission pipelines, located near the intersection of California Avenue and El Camino Real. SFPUC anticipates the work to occur from April 1 - April 8, 2024.The work requires one- or two-lane closures on El Camino Real from Cambridge Avenue to California Avenue during different times as day and night work progresses. Anticipate both vehicle traffic in and around the area, and pedestrian crossings impacts at the California Avenue and El Camino Real intersection.

*Timing and sequencing may be extended and/or change due to weather or other conditions.

Learn more here.

Other Work on El Camino Real Underway or Planned:

  • Page Mill Road near El Camino Real - The City's sanitary sewer replacement project continues, and lane closures are in effect on Page Mill Road heading towards Highway 280.
  • Different Points on El Camino Real- Caltrans continues ADA updates/shoulder and sidewalk work at different points along El Camino Real. Temporary parking and shoulder closures in effect.
  • Arastradero/Charleston at El Camino Real intersection- Staff anticipate work to occur soon. This page will be updated when this work is scheduled.
Tagged as: