City of Fort Lauderdale, FL

03/22/2024 | Press release | Distributed by Public on 03/22/2024 13:54

Emergency Water Main Replacement Project in Downtown Fort Lauderdale

The City of Fort Lauderdale is working with Murphy Pipeline Contractors to replace aging water mains in Downtown Fort Lauderdale along:

  • N New River Drive E from Andrews Avenue to SE 5th Avenue
  • SE 5th Avenue from N New River Drive E to Las Olas Boulevard
  • SE 3rd Avenue from N New River Drive E to Las Olas Boulevard
  • SE 4th Street from SE 3rd Avenue to SE 5th Avenue

The new pipes will measure 10 inches in diameter and be made of high-density polyethylene (HDPE), which is a non-corrosive material that will help reduce the impacts of groundwater and saltwater. The project will include establishing temporary connections to ensure that water service is maintained throughout construction.

Crews will primarily install the new water mains utilizing trenchless technology to minimize the impact on the community. This method is more efficient than traditional open-cut construction and will expedite the completion of the project. Excavation will be necessary in some areas. Work is expected to begin at Las Olas Boulevard and SE 5th Avenue and continue southwest.

Construction began on Monday, October 2, 2023. Work is generally taking place during the day between 10 a.m. and 7 p.m. Some overnight work may be required. This schedule is subject to change based on inclement weather or other unforeseen circumstances. The contractor completed the pipe installation during the week of February 5, 2024. Restoration is expected to be completed by the end of March.

Recently Completed Activities

  • Contractor continued cleaning and final restoration.
  • Contractor worked on permanent pavement markings.
Upcoming Activities (Through 3/29/24)
  • Contractor to complete permanent pavement markings on N New River Drive and SE 3rd Avenue.
    • Traffic control personnel will direct traffic in the area while lanes are closed for this operation.
  • Contractor will continue final restoration efforts.

Traffic Impacts

  • One lane in each direction of each street within the project limits may be closed during construction. Traffic control personnel will direct traffic as needed. No full closures/detours are expected.
  • Please follow posted signs and drive with caution in the area.

We apologize in advance for any inconvenience and thank our neighbors for their patience during construction.

For more information or questions, contact:

William Power, City of Fort Lauderdale Senior Project Manager
[email protected]

City of Fort Lauderdale Neighbor Service Center
954-828-8000 or [email protected]