City of Modesto, CA

09/22/2021 | Press release | Distributed by Public on 09/22/2021 16:40

Weekly Traffic Impact Report Week of September 22, 2021

State Route 132 West Freeway Expressway Phase 1 Project

Project Status

For more information please visit the State Route 132 Project website.

Traffic Impacts

  • The Southbound 99 off ramp at Maze 132 (L Street) will have a full closure.
  • Southbound motorists will be asked to exit at the following "Central Modesto" exit.
  • Full 24 hour a day closure on the Kansas Avenue / Mercy Avenue intersection. This closure is expected to last 10 weeks. The construction will require major excavation and construction in the middle of the intersection. For both safety and efficiency, the intersection will be fully closed to all public traffic.
  • Detour signs will be provided. The following traffic detours will be in place:
  • The primary detour route around the full intersection closure will include Morse Road, Woodland Avenue, and Carpenter Avenue.
  • To further improve traffic circulation during the construction, Rosemore Avenue which has been closed South of Kansas Avenue since early 2020,
    will be open to traffic allowing greater access in the area.
  • Night time full freeway closures and detours of State Route 99 between Kansas Avenue and G Street.
  • These full closures of Highway 99 will be used to remove the overhead falsework that has supported the construction of the new bridge superstructure over the past six months.
  • Night time closures and detours are scheduled to start on Wednesday night September 22, 2021 and are expected to last until October 12, 2021 from 10:00 p.m. to 5:00 a.m.
  • The full closures will only take place on Monday nights thru Thursday nights.
  • There will be no full closures of State Route 99 on Friday, Saturday, or Sunday nights.
  • In addition, the northbound and southbound directions will not be simultaneously closed.
  • Southbound closures and detours are expected to last until Thursday September 30th.
  • Northbound closures and detours are scheduled to begin Monday night October 4, 2021 and are expected to last until Tuesday October 12, 2021.
  • As always these dates are subject to change.
  • California Highway Patrol and the Police Department will be providing assistance along the detour routes.
  • There will be flaggers at key intersections providing direction.

New Jennings Water Quality Control Plant Entrance/Exit Project

Project Status

Work is in progress. Project is expected to be completed by the end of October 2021.

Traffic Impacts

Construction signs will be in place for the road closure:

  • Jennings Road has been re-opened to motorists.
  • Entrance/Exit road is now open. Partial road closures to be expected through the end of October, as needed.
  • Motorists to be advised of new traffic signal installed and is fully operational.

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Scenic Drive Pavement Rehabilitation Phase 1 Project

Project Status

Work is in progress. Project is expected to be completed by the end of December 2021.

Traffic Impacts

Traffic control will be in place:

  • Scenic Drive from Lakewood Avenue to Claus Road

Motorists are advised to drive slowly with caution and use alternate routes when possible.

PG&E Project

Project Status

Work is in progress. Project is expected to be completed by end of October 2021.

Traffic Impacts

Construction area signs will be in place.

  • Lane shifts and lane closures will be in place mostly on east and west bound Woodland Avenue and Coldwell Avenue from Graphics Drive to Tully Road.
  • Some lane closures will be in place on 9th Street north and south bound sides.

Motorists are advised to drive slowly with caution and use alternate routes when possible.

PG&E Project

Project Status

Work is in progress. Project is expected to be completed by end of October 2021.

Traffic Impacts

Construction area signs will be in place.

  • Lane shifts and lane closures will be in place mostly on east and west bound Clevenger Drive from Carver Road to Tully Road.
  • Some lane closures will be in place on Carver Road and Tully Road north and south bound sides.

Motorists are advised to drive slowly with caution and use alternate routes when possible.

PG&E Project

Project Status

Work is in progress. Project is expected to be completed by end of October 2021.

Traffic Impacts

Construction area signs will be in place.

  • Lane shifts and lane closures will be in place mostly on east and west bound Clevenger Drive from Carver Road to Tully Road.
  • Some lane closures will be in place on Carver Road and Tully Road north and south bound sides.

Motorists are advised to drive slowly with caution and use alternate routes when possible.

Well Surface Improvements Project

Project Status

Work is in progress.

Traffic Impacts

  • A portion of Brenner Way is closed from Conant Avenue to the alley until October 1st, 2021.

Motorists are advised to drive slowly with caution and use alternate routes when possible.