I-84 bridge repairs to begin next week in Gooding, Jerome, Minidoka and Cassia counties

4/21/2021

Contact:
Jessica Williams
ITD Office of Communication
208 886-7806
[email protected]

I-84 bridge repairs to begin next week in Gooding, Jerome, Minidoka and Cassia counties

SHOSHONE-Repairs to structures along I-84 in South-central Idaho are expected to begin Monday, April 26.

Over the coming months, ITD will resurface thirteen bridges and nine overpasses, as well as perform other minor maintenance activities, to keep them in service longer. For most bridges, traffic will be reduced to one lane. As work shifts from one bridge to another, traffic patterns will also change. Drivers should expect reduced speeds throughout the area and watch for crews during working hours.

Two overpasses in Minidoka County will be completely closed during construction.

'The overpasses at 500 West and Meridian Road will be closed for about three weeks, but not at the same time,' ITD project manager Bruce Christensen said. 'These detours are expected in late May and mid-June.'

As those closures approach, another release will be sent.

Closing the two overpasses will allow crews to complete work sooner, reducing project costs and lessening the overall impacts to travelers.

Click here to see a map of the anticipated detours.

Construction on all bridges is expected to be finished by October of this year. The general contractor is Cannon Builders.

# # #