04/10/2024 | Press release | Distributed by Public on 04/10/2024 13:16
Negative Declaration
Livingston County - The Livingston County Water and Sewer Authority (LCWSA), as lead agency, has determined that the proposed Countywide Water System Improvements will not have a significant adverse environmental impact. The action involves the following:
1. ARS interconnection: Installation of approximately 17,000 to 22,000 linear foot of water main to connect the existing Consolidated Water District in the Town of Groveland to the existing American Rock Salt water system and water storage tank.
2. Groveland Station interconnection: Installation of approximately 2,000 linear foot of water main connecting the existing Groveland Station water main and the existing water main in the Town of Groveland.
3. Additional storage at Shelly: Replacement of the existing Shelly Road water storage tank with a new, higher capacity water storage tank.
4. County-wide improvements: SCADA Controls systems upgrades and improvements throughout the water system, installation of TTHM removal systems at several water storage tanks throughout the consolidated water district, and installation of new water meters for LCWSA customers throughout the consolidated water district.
5. Big Tree Services: The LCWSA is proposing a change in the scope of work to include the transfer of water services along a portion of Big Tree Road in the Town of Livonia from an existing 10 inch transmission main installed in 1966 to the newer transmission main on the opposite side of the roadway.
The project is located Towns of Livonia, Conesus, and Groveland, New York.
JasonMolino
Livingston County Water & Sewer Authority
1997 D'Angelo Drive
Lakeville, NY14480