The heart of Abilene is poised for transformation as the City of Abilene gears up for the Cypress Street Improvement Project. This ambitious endeavor, spanning from North 1st Street to North 5th Street, will see comprehensive roadway and sidewalk reconstruction, breathing new life into the historic thoroughfare.
On Thursday, the Abilene City Council approved a guaranteed maximum price (GMP) of $9,548,653 for the project with Teinert Construction.
City Council's approval of the GMP for the Cypress Street Improvement Project allows the City to provide Teinert with a Notice to Proceed, allowing construction to begin within 5 days of receiving the Notice. Road closures in the affected areas are expected to begin within the next week.
Planned street closures, alleyway access, and sidewalk access for the first phase of the Cypress Street Improvement Project extending through September 2024 will include:
Work on Cypress Street will pause for the months of October, November, and December 2024 to minimize the disruption to local businesses during the holiday months. Phase 2 of the Cypress Street Improvement Project will begin in January 2025. The total construction time for the Cypress Street Improvement Project is 18 months.
To subscribe to information and updates on the Cypress Street Improvement Project and other Downtown Abilene news, click here or visit the "Communications" tab at www.abilenetx.gov and sign up for updates at "Notify Me." Questions or concerns about the Cypress Street Improvement Project can also be directed to the City of Abilene's Downtown Coordinator at [email protected].
Click here for printable PDF of the Cypress Street Improvement Project Phase 1 map.